banner
 
arrow pointer TDGC Website
 
Total Visitors since
28 Aug 2003: 380787
 
Valid XHTML 1.0!
 
Valid CSS!

Tdgrocks - Hardware Setup


Dscn1096_21.jpg enlarge photo

All components for the PC cluster were delivered on 20/2/2003 and stored in room SCT719 and SCT719A, HKBU.

Dscn1098_21.jpg enlarge photo

First day for the rack installation, 17/3/2003. 3 sets of UPS were placed at the bottom of each rack.

Dscn1099_21.jpg enlarge photo

At the end of the day, a lot of components were still waiting for installation.

Dscn1104_21.jpg enlarge photo

Rails were installed inside each rack. Each pair of rails was responsible for holding a 2U server, which is a cluster node.

Dscn1107_21.jpg enlarge photo

Cluster interconnect: Extreme BlackDiamond 6816 Gigabit ethernet switch.

Dscn1108_21.jpg enlarge photo

Cluster interconnect was also installed in a Dell rack.

Dscn1100_21.jpg enlarge photo

Another view of the racks, with the UPS successfully installed.

Dscn1114_21.jpg enlarge photo

Cluster interconnect comes with 2 power supplies.

Dscn1117_21.jpg enlarge photo

Cluster nodes were installed into each rack, according to the order of their serial numbers (asset tags) for easy management in the future.

Dscn1124_21.jpg enlarge photo

16 servers (cluster nodes) and 3 sets of UPS filled up one rack.

Dscn1126_21.jpg enlarge photo

At the end of the first day, all racks were moved to SCT713. HKBU. And they were REAL heavy.

Dscn1127_21.jpg enlarge photo

One occupied rack in position.

Dscn1141_21.jpg enlarge photo

6 racks filled up with cluster nodes were placed in position.

Dscn1138_21.jpg enlarge photo

The 1U LCD monitor and keyboard were connected to the master node.

Dscn1142_21.jpg enlarge photo

Started to lay network cables (CAT 6) from the servers in one of the racks on 23/3/03.

Dscn1156_21.jpg enlarge photo

Each cluster node would be soon connected with ethernet switches (up: fast ethernet network for system management, down: gigabit ethernet network for computation), through the network cables.

Dscn1157_21.jpg enlarge photo

There are altogether 128 pieces of network cables in the cluster.

Dscn1162_21.jpg enlarge photo

A pair of network cables were plugged into the back of each server.

Dscn1167_21.jpg enlarge photo

At the end of the fourth day (20/3/2003), all network cables were plugged into the gigabit and fast ethernet switch. See how neat they look!

Dscn1171_21.jpg enlarge photo

When uncovering the front panel of each server, you will see a LCD display showing the basic hardware information.

Dscn1172_21.jpg enlarge photo

For the ease of initial checking, a keyboard with built-in mouse (to the right side of the keyboard) and an external monitor were used to connect to the server through the VGA and keyboard ports in front of the chassis.



Privacy Policy    ©2002-2024 Hong Kong Baptist University. All Rights Reserved.